3.11 Dave Fletcher (See Problem 3.10) Was Able To Determine The Activity Times For Constructing His Laser Scanning Machine. Fletcher Would Like To…

3.11

Dave Fletcher (see Problem 3.10) was able to determine
the activity times for constructing his laser scanning
machine. Fletcher would like to determine ES, EF, LS, LF, and
slack for each activity. The total project completion time and
the critical path should also be determined. Here are the activity
times:

Get Your Custom Essay Written From Scratch
Hello Students, Our team can help you complete your assignments and reduce the stress of studying. We here provide you a highly qualified team who can help you in many works like thesis,reports,assignments,online exams and many more. Our team is available to help you 24x7 worldwide. We work around the clock to ensure students get high quality work at affordable rates and are on time. To ensure that the work is authentic, we offer plagiarism-free work.
Just from $13/Page
Place an Order

ACTIVITY TIME (WEEKS) ACTIVITY TIME (WEEKS) (letter is activity and number is time)

 

 

Get Assignment Writing Help

Our experts are ready to complete your assignment, course work. essay, test, dissertation, research paper, quiz

Get Started

A6       E 4
B 7       F 6
C 3      G 10
D 2       H 7

 

3.17

Bill Fennema, president of Fennema Hospitality, has

developed the tasks, durations, and predecessor relationships in

the following table for building new motels. Draw the AON network

and answer the questions that follow.

 

 

Activity   predecessor optimistic       Most       pessimistic

likely       OPTIMISTIC

MOST

LIKELY PESSIMISTIC

A        —      4       8        10

B       A        2       8         24

C       A        8      12       16

D       A        4       6         10

E       B         1      2         3

F       E,C      6       8        20

G     E, C     2      3         4

H       F          2      2         2

I        F          6      6         6

J      D,G,H    4     6        12

K      I,J         2      2        3

 

c) Based on the calculation of estimated times, what is the critical

path?

d) What is the estimated time of the critical path?

e) What is the activity variance along the critical path?

f) What is the probability of completion of the project before

week 36?

 

to be completed in excel on seperate pages

Needs help with similar assignment?

We are available 24x7 to deliver the best services and assignment ready within 3-4 hours? Order a custom-written, plagiarism-free paper

Order Over WhatsApp Place an Order Online

"Do you have an upcoming essay or assignment due?


Get any topic done in as little as 6 hours

If yes Order Similar Paper

All of our assignments are originally produced, unique, and free of plagiarism.

Stuck with a Question?

Get it solved from our top experts within 8 hrs!

Ask Your Question Now!